SARPRAS-EV-01
Drawing submission register
Received, returned and approval dates used to follow drawing submissions. The drawing-description columns are excluded from this extract.

Sarpras II, IKN / Indonesia / 2024
Reporting, submission tracking and meeting follow-up within the consultant-side construction management team.
Prior professional experience with the organisation named below. This is not a ConstructFree client engagement or Australian project.
ADHI–PENTA KSO was the contractor. Contractor-prepared records entered the consultant-side construction management process for review, monitoring and follow-up. Theodore supported reporting, submission tracking and coordination of outstanding information within PT Virama Karya (Persero) / KSO VK–CEC.
Responsibilities

Original project wording, with a short explanation of what each extract shows.
SARPRAS-EV-01
Received, returned and approval dates used to follow drawing submissions. The drawing-description columns are excluded from this extract.

SARPRAS-EV-02
Records planned and actual progress alongside a site constraint for the project team to review. This is an extract of meeting minutes, not a separate weekly report.

Previous professional experience with Virama / KSO VK–CEC in Indonesia. These were functional administration duties; the project roster title was Operator CAD/BIM 3. Contractor-prepared records are not claimed as Theodore’s own work. Approval authority remained with the authorised project team.
Related services
A useful register tells the PM when a drawing arrived, whether it has been returned and who needs to respond. The weekly report then brings the open items together.
Tell us which project, which registers and where the follow-up is getting stuck.