Installed quantities and close-out checklist
Compares package quantities with planted quantities and records defects, outstanding work and completeness by vegetation type. The selected rows show the checks used before close-out.

RTJM & HPK II landscape packages / Indonesia / 2024–2025
Supplier follow-up, quantity checks and close-out records across separate landscape packages.
Prior professional experience with the organisation named below. This is not a ConstructFree client engagement or Australian project.
Landscape work across separate sites required current quantities, supplier updates and records for staged handover. The records identify RTJM Package C, Kavling 25–28; RTJM Area B, Persil 105; and HPK Tahap II, Package B as separate packages.
Responsibilities

Original project wording, with a short explanation of what each extract shows.
RTJM-EV-01
Compares package quantities with planted quantities and records defects, outstanding work and completeness by vegetation type. The selected rows show the checks used before close-out.

Previous Project Manager assignment under PT Rafli Putra Bungsu in Indonesia. The selected record relates to the RTJM landscape work.
Related services
Procurement tracking needs more than an order date. The item, quantity, latest supplier update and handover record need to agree with what happened on site.
Tell us which project, which registers and where the follow-up is getting stuck.