The weekly report your PM can actually use.

Build a concise weekly construction report around items needing attention, decisions and traceable source records.

3 min / PROJECT NOTE

Set a reporting cut-off

State the date that the report represents. Registers continue to change, so a report needs a consistent point in time. Explain whether overdue means before that date and how the lookahead window is calculated.

Lead with the items needing attention

Put unanswered queries, approval dependencies and delivery risks ahead of routine completed work. For every item needing attention show the source reference, responsible party and next action. A short decision list is easier to use than a pasted register.

Keep the source within reach

Link back to the controlled record. The report is a view of that information, not a second place to maintain it. If something changes after issue, record the change in the source and flag a material correction through the agreed channel.

Finish with decisions and responsibility

Separate work the administrator will follow up from decisions the PM needs to make. End the report with those decisions, owners and dates. The next reporting cycle should explain which open items were resolved and which still need a decision.

See an example

Explore fictional registers and a downloadable weekly report in the sample Control Centre.

Open sample workspace

Discuss your project.

Tell us which project, which registers and where the follow-up is getting stuck.

Discuss your project

Cookie preferences

Essential site features use your browser storage to remember these choices. Optional analytics is off until you choose to allow it.

We do not send form content to analytics. Read the privacy policy